Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner. Facebook Messenger An icon of the facebook messenger app logo. Facebook An icon of a facebook f logo. Facebook Messenger An icon of the Twitter app logo. LinkedIn An icon of the LinkedIn logo. WhatsApp Messenger An icon of the Whatsapp messenger app logo. Email An icon of an mail envelope. Copy link A decentered black square over a white square.

‘It’s not gone well’: Cromarty Firth Hutton legs removal plagued by dispute and HSE orders

The legs of the Hutton TLP.
The legs of the Hutton TLP.

A project to remove an “eyesore” from the Cromarty Firth has stalled, having been plagued by business disputes and a flurry of health and safety orders.

But Nerida, the company in charge of the Hutton project, has said it is confident of finally getting back on track despite the tribulations.

Work got under way last year to remove the 20,000-tonne Hutton structure – a hull and six legs , also known as a tension leg platform (TLP) – which had been deserted in the channel in 2009.

After changing hands several times, it was finally acquired by freight specialist Nerida and Messiah Decommissioning, who vowed to complete its dismantling at the Queen’s Dock site at the Port of Cromarty Firth.

Beginning in May 2021, the operation was expected to last 12 months and had the backing of stakeholders including the Scottish Environmental Protection Agency (SEPA), the then-Oil and Gas Authority and the port management.

However, more than a year on, the project remains unfinished, having been stalled by a contractual dispute, the departure of contractors and a series of health and safety orders.

Chief amongst these developments is the loss of venture partner Messiah which, according to Nerida managing director John Townley, left the project following an unspecified “contractual dispute” between the two firms, leaving Nerida with sole control of the asset.

This was confirmed by Messiah chief executive Tony O’Sullivan, who said his company had removed several thousand tonnes of scrap from the site in December, before handing the hull back to Nerida in early January.

Messiah no longer has any involvement in the project.

Mr Townley said Nerida had then appointed an unnamed subcontractor to carry out the work, only to have work stopped by the Health and Safety Executive (HSE) – an intervention he suggested was related to the competence of the newly appointed firm.

“We had a big problem in that I got certain people to come in to do the job, which I believed they were capable of doing, but the HSE came down and shut us down,” he explained. “So at that point in time, I had to change the team.”

HSE inspectors issued the site with five notices in late April 2022, two of which called for an immediate stoppage of work.

HSE prohibition notices show that Nerida and its contractors “failed to ensure that the demolition process for the Hutton platform take into account structural issues prior to cutting and detaching elements leading to instability of the structure.”

A second order said they had “failed to ensure that effective planning, management and monitoring are in place on site,” that activities were “poorly controlled” and that risks including “falls from height, structure stability, drowning and fire” were not adequately controlled.

Improvement orders were also issued for insufficient fire risk assessments, failure to assess the risks from fumes generated during the steel burning process and an assessment that contractors had “failed to ensure that persons working [on] site have the skills, knowledge and experience to fulfill the roles they have been appointed to undertake.”

The HSE confirmed that the temporary shutdown of the site in April was as a result of its enforcement action.

A spokesperson added: “HSE has been involved with a pro-active intervention with the owner of the Hutton Hull for over 12 months as part of a wider strategy to engage with the emerging sector of decommissioning and dismantling offshore structures.”

It pointed to a guidance document outlining how it oversees interventions in decommissioning operations.

Two workers stand alongside the 20,000 tonne structure at Queen’s Dock. 29 May 2021

‘It should’ve been demolished now’

Following co-operation with the HSE, work at the Hutton resumed in late May, with Nerida taking sole oversight of the operation.

In early June, Mr Townley acknowledged the process had not gone as planned.

“This has been a difficult process for us and for everybody, and it’s not gone well.

“It should’ve been demolished now, it should be a few bits and pieces left floating,” he said.

“What I’ve learned from it is that you can’t do this half-cocked, you’ve got to bring the right people in.”

However, he is confident the job will be completed “by the end of the year”.

Around 16 people are currently working on the project, not including external consultants, he said.

As of the time of writing, the fourth of the TLP’s six legs is about to be demolished, leaving three legs and the 95 square metre substructure.

Once all remaining towers are dismantled, Mr Townley said attention would turn to the floating pontoons, which the team plans to cut into sections that could be lifted onto the quayside for break up.

Despite the considerable setbacks, Mr Townley also remained optimistic about the wider potential of the decommissioning sector.

“It’s a very interesting project and worthwhile being involved in. The key issue is being able to make it financially worthwhile,” he said.

“We’re not a big company, it’s a fairly small operation… this is a new thing we’ve taken on – out of necessity – but the further we go along I can see more opportunities in the area.”

The Port of Cromarty Firth declined to comment on the project.