Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner. Facebook Messenger An icon of the facebook messenger app logo. Facebook An icon of a facebook f logo. Facebook Messenger An icon of the Twitter app logo. LinkedIn An icon of the LinkedIn logo. WhatsApp Messenger An icon of the Whatsapp messenger app logo. Email An icon of an mail envelope. Copy link A decentered black square over a white square.

AWPR contractors could be hauled in front of Scottish Government committee over delays

The northern route of the AWPR at Balmedie connecting with the A90.
The northern route of the AWPR at Balmedie connecting with the A90.

Calls have been made for the contractors of the Aberdeen bypass to appear before Holyrood to explain the delays.

Last week, Transport Secretary Michael Matheson told parliament that Aberdeen Roads Ltd (ARL) had pushed back the “late autumn” completion date of the £745million AWPR and now hoped to have it open in December.


>> Keep up to date with the latest news with The P&J newsletter


Mr Matheson said a “definitive date” for its opening could not be offered because work to repair defects on the new River Don bridge could be further delayed.

The transport secretary blamed the ARL contractors for their “simply unacceptable” failure to progress his demand to open the 19-mile Craibstone to Stonehaven section, ahead of the completion of the Don crossing.

However, he said such a move would require a variation of the original contract to be agreed by ARL.

Now Aberdeen Donside MSP Mark McDonald has written to Edward Mountain, the convener of the Scottish Government’s Rural Economy and Connectivity committee, appealing for him to get the committee to Holyrood to answer questions “as a matter of transparency”.

Mr McDonald said: “It is important that the public have answers as to why the delays that have taken place have occurred, what is being done to address these, and whether the contract variation that would allow Craibstone to Stonehaven to open early will take place.”

Meanwhile Aberdeen Central MSP Kevin Stewart has written to Galliford Try, which works under the umbrella of ARL alongside Balfour Beatty, asking the company to address the “contractual issue” which is preventing drivers from using the new multi-million pound road.

He said: “We all know how vital the AWPR will be to the north-east, and I’m angered that Galliford Try have let folk down by deliberating not sorting this matter out.

“The SNP Scottish Government started, and will deliver, this immense project and it’s high time the contractor got its act together.”

Last night, a spokesman for Transport Scotland said: “While there are technical issues to be resolved, this should not prevent the opening of sections of the road which are ready, and we have been pursuing a variation in the contract with Aberdeen Roads Ltd to allow this to happen.

“The contractor must stop its deliberations on this and open the road as soon as possible, so the benefits can be felt by north-east motorists and communities.”