Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner. Facebook Messenger An icon of the facebook messenger app logo. Facebook An icon of a facebook f logo. Facebook Messenger An icon of the Twitter app logo. LinkedIn An icon of the LinkedIn logo. WhatsApp Messenger An icon of the Whatsapp messenger app logo. Email An icon of an mail envelope. Copy link A decentered black square over a white square.

Massive Cruachan power station expansion project on hold – until housing and traffic conditions are met

Argyll and Bute Council is objecting to the expansion of Cruachan Power Station - until special conditions are met.
Image: Sandy McCook/DC Thomson
Argyll and Bute Council is objecting to the expansion of Cruachan Power Station - until special conditions are met. Image: Sandy McCook/DC Thomson

Argyll and Bute Council is objecting to a £500million proposal for a second power station at Cruachan Dam, Loch Awe.

This will only be until conditions protecting the local housing market and minimizing traffic disruption are met.

The last-minute recommendation to the council’s planning committee was made by officers as a result of legal advice.

A new quayside will be created on the north shore of Loch Awe.

An objection will stand until developer Drax can show how it will protect the local housing market during the project – which will see hundreds of construction workers based in the area.

Drax will also have to explain how traffic disruption will be kept to a minimum.

Originally planners encouraged members not to object to the biggest Scottish energy infrastructure project in 40 years, subject to a list of conditions.

However, the officers decided to reword their recommendation, instead advising the council to object, until various conditions are met.

Millions of tonnes of rock to be excavated from mountain

The nationally significant development will see an estimated 2.3 million tonnes of rock removed from the famous “Hollow Mountain”.

Of this, 600,000 tonnes will be used to form a new quayside by the loch, which will store rock and house infrastructure.

Conditions the council and other consultees have proposed include measures which will mitigate the impact of construction during the major project.

These include traffic, environmental impacts and the pressure on the local housing market due to accommodation required by workers.

Councillor Kieron Green, chairman of the planning committee.

During the six year hydro power project, a total of 357 jobs will be supported. At peak construction time there will be around 300 workers on the site.

Kieron Green, chairman of the planning committee, said: “We are recommended to object, but we all are aware of the context of the objection.

“I move that we object, until the conditions recommended by the planners and other consultees are met.”

Councillors agreed with him unanimously.

What will the project consist of?

A huge new cavern in the mountain containing turbines and generators will be large enough to fit Big Ben on its side.

There will be an upper control works adjacent to the reservoir, a tunnel network and underground waterway system.

The existing substation will be extended and a new lower control works will be built.

A quayside will be constructed on the shore of Loch Awe and there will be above ground administration and storage buildings.

Cruachan Dam.

All of this work will allow Drax to double the energy generated at Cruachan.

There will be no changes to the existing dam, which is a listed building. Much of the infrastructure will be below ground.

Permission from the Scottish Government’s Energy Consents Unit is required for the expansion. The council is among the statutory consultees.

David Moore, planning officer, said that the Scottish Government and the council recognize the need to tackle climate change.

Officers will be ‘pushing very hard’ to keep road disruption to a minimum

He said both bodies have extremely supportive policy for the Cruachan proposal.

Mr Moore said: “We will be pushing very hard to make sure there is minimal impact on the free flow of traffic on the A85 during construction. It is in everyone’s interest that we minimize that.”

He also called for a housing strategy, where the developers will explain how they will ensure no harm will come to the local housing market.

Conditions asking for a construction traffic management plan and a traffic impact assessment will help protect the road network.

Are you interested in more exclusive and breaking Highland and Islands news from the P&J? If so, why not join our dedicated Facebook page here

Conversation