Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner. Facebook Messenger An icon of the facebook messenger app logo. Facebook An icon of a facebook f logo. Facebook Messenger An icon of the Twitter app logo. LinkedIn An icon of the LinkedIn logo. WhatsApp Messenger An icon of the Whatsapp messenger app logo. Email An icon of an mail envelope. Copy link A decentered black square over a white square.

AWPR finished at last – but a contract row is holding up the opening

The Scottish Transport secretary has cautioned Aberdeen Bypass contractors against “using the north-east’s enthusiasm for the road” to “apply pressure” for extra money or “cut corners” as final work is carried out on the last remaining piece of the multi-million pound project.

Aberdeen Roads Limited (ARL) is nearing the end of construction on the Don Crossing, the final part of the Aberdeen Western Peripheral Route (AWPR).

Physical work on the remaining four-and-a-half miles of the bypass is now finished and further examinations are due to take place in the following days before it is finally opened to the public.

But last night the Scottish Government’s cabinet secretary for transport, Michael Matheson, told the contractors that the road must absolutely not be opened until final safety and structural examinations are concluded.

And he also warned that the desire of motorists, city and regional leaders and the government to see the road opened in full could not be used as leverage by ARL to pressurise Transport Scotland into paying out extra cash.

Mr Matheson said: “I am pleased to confirm the AWPR contractor has undertaken the remaining physical works on the Don crossing, with some survey works and safety checks being undertaken over the next week.

“In particular, I would like to thank the workforce for their efforts, especially at this time of year, in often challenging conditions.

“However, we continue to await ARL management providing the necessary technical assurances required to allow the road to open.”

More than 20 miles, or 85% of the AWPR has already opened to the public, providing faster journeys from Stonehaven to the airport.

The enormous project has, however, been faced with numerous delays since construction commenced in 2015, including the collapse of construction giant Carillion, a former member of ARL.


>> Keep up to date with the latest news with The P&J newsletter


Designed to reduce traffic congestion in Aberdeen and improve traffic flow around the city,it was originally due to cost £745 million.

Representatives from the ARL consortium of Balfour Beatty and Galliford Try did, however, tell the Scottish Parliament in December that they would seek compensation from Transport Scotland for extra money spent on top of the original fixed contract price.

Concerns have been raised that the final price tag for the entire project could be more than £1 billion if the contractor’s compensation claim is successful – however, it is understood that ARL has not yet provided sufficient evidence to the Scottish Government to substantiate its claim.

Mr Matheson said the final stretch of the bypass would not open until Transport Scotland was happy that the “public purse is protected”.

He added: “Taxpayers have the right to expect high standards of quality when they pay for new infrastructure from reputable international construction firms and also, to not be penalised for mistakes of these contractor’s own making.

“Since it reported that more extensive remedial work was necessary on the Don Crossing in late October last year, ARL has been well aware that the technical assurances regarding the longer-term impact of these complex repairs to the bridge defects were required.

“Transport Scotland continues to work constructively with ARL, but I have been very clear and consistent that under no circumstances will the final section open until our technical experts are satisfied the public purse is protected.

“This is not the first time we have been forced to caution ARL against attempting to use the North East’s enthusiasm for the road to apply pressure and cut corners on important contractual issues that simply cannot be avoided.”