Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner. Facebook Messenger An icon of the facebook messenger app logo. Facebook An icon of a facebook f logo. Facebook Messenger An icon of the Twitter app logo. LinkedIn An icon of the LinkedIn logo. WhatsApp Messenger An icon of the Whatsapp messenger app logo. Email An icon of an mail envelope. Copy link A decentered black square over a white square.

A9 roadworks at the end of the month

The A9 near Tomatin
The A9 near Tomatin

Delays are expected on the A9 later this month during three day resurfacing works near the Tomatin junction.

The £343,000 project to replace the road surface northbound between Findhorn Bridge and Tomatin will take place between Monday, June 23 and Thursday, June 26.

The half-mile works will be carried out 24 hours a day to minimise the overall construction period and to reduce disruption to users of the Inverness to Perth trunk road.

Road management group Bear Scotland have said that this will mean the works will last three days, rather than the two weeks which would have been needed to complete the job with 12 hour shifts.Bear Scotland have also confirmed that the work will use an innovative new surface developed in Germany for the work on the A9.

The surface is designed to have a higher than usual friction rating, in a bid to reduce stopping distance and improve skid resistance.

It is designed to reduce stopping distances and reduce road noise for motorists.

Bear Scotland also made use of German surfacing to complete the Kessock Bridge roadworks further north on the A9.

The material used at Tomatin is similar but not identical to the gussasphalt used in the bridge repairs.

Eddie Ross, Bear Scotland’s north west unit representative said: “These essential resurfacing works will improve the condition of this section of the A9, which is nearing the end of its serviceable life.

“The project has been designed to improve the structural integrity and prolong the life of this section of road.

“We have carefully designed this programme so that disruption to road users on this key strategic route is minimised.

“A contraflow system will be in operation throughout the duration of the works which will also afford the maximum protection to the workforce and road users alike.

“We would encourage motorists to plan their journeys in advance, check the Traffic Scotland website for up to date information, and to allow extra time for travel.”

A reduced speed limit of 50mph will be in place through the contraflow section, while local 30mph speed limit restrictions will also be in force at the carriageway crossover points.