Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner. Facebook Messenger An icon of the facebook messenger app logo. Facebook An icon of a facebook f logo. Facebook Messenger An icon of the Twitter app logo. LinkedIn An icon of the LinkedIn logo. WhatsApp Messenger An icon of the Whatsapp messenger app logo. Email An icon of an mail envelope. Copy link A decentered black square over a white square.

Island communities face more cancelled ferries and reduced car capacity

The mezzanine level on the MV Hebrides ferry requires higher numbers of staff (Photo: Arthur Campbell/Shutterstock)

Island communities will have to accept a reduction in journeys or reduced capacity next year, according to the Scottish Government transport minister.

Changes to the timetable for the 2022 season are currently out for public consultation, but it has been warned services could be removed in off-season because of a lack of staff.

The affected routes, sailing from Tarbert in Argyll and Lochmaddy in North Uist could still run on the current timetable, but without mezzanine decks — the closure of which would drastically cut car capacity on board.

Transport minister Graeme Dey said the reductions would be required to allow staff adequate rest between sailings, after concerns were raised about reduced services by Western Isles MSP Alasdair Allan.

‘Required rest’

Mr Dey said: “Increasing demand on the route has led to CalMac deploying mezzanine decks more frequently, and that has led to challenges for loading and off-loading on the current timetable.

“Any delays to sailings have knock-on effects, often requiring the need for sailings to be cancelled in order to ensure crews to get the required hours of rest.

Graeme Dey

“This option is therefore being developed to allow the mezzanine decks to be fully deployed with some amendments to timetables, resulting in the removal of the shoulder off-peak season in having a consistent timetable for the whole summer period.

“However, if the community do not want this, the summer 2021 timetable will remain in place although the mezzanine deck will not be deployed in order to avoid delays and cancellations.”

Frustrations

Island communities have already been left frustrated by cancelled and reduced services as a result of the pandemic, and the ongoing impact Coronavirus has had on their economies.

An extra ship had to be chartered in the summer — which subsequently broke down — to meet demand, after capacity was reduced to 35% as part of the government’s restrictions.

New ferries delayed

A boat for the Hebrides, ordered in 2015, are still to be completed and delivered, despite the company building the ships coming under Scottish Government ownership.

Orders for two ships, built in Port Glasgow and set to sail for communities on the Clyde and the Hebrides, were placed by CMAL (Caledonian Maritime Assets Ltd) with Ferguson Marine Engineering Ltd (FMEL) in October 2015.

The cost of completion increased from an initial fixed price of £97 million to between £192.8m and £196.8m.

Each ferry, named 801 and 802, is not expected to launch for service until 2022 and 2023, respectively — as much as 49 and 55 months late, respectively.

A report by the Rural Economy and Connectivity Committee stated there had been a “catastrophic failure” in the procurement process, but islands minister Paul Wheelhouse subsequently rejected the findings.